Update on Construction Previous item Corporate Pickleball Event

Update on Construction

2 April 2023: The driveway and parking is complete. Interiors of the kitchen, washrooms and pro shop will be complete by Easter. The court roof system arrives April 20th and we will then spend roughly 3 weeks building the structure as well as painting the courts, completing the landscaping, fitting out the shop and getting final approvals. Still on track for an opening in the second half of May.